BASF FA 561

Fuel depot

Location

Friesenheimer Insel, Werksgelände BASF, Ludwigshafen Deutschland

Construction year

2014

Project description

The designed tank is used for the storage of 20,000 m³ of water-polluting substances and was classified as a "LAU" facility according to VAwS. The retention in the sense of a secondary barrier was designed and constructed as an uncoated impermeable surface in accordance with DAfStb guideline BUmwS as a circumferential combined reinforced concrete containment space.

Optimisation with SFRC
  • Reduction of the slab thickness by optimising the position of the neutral axis in the cross-section towards the tensioned side (increase of the bending pressure zone) -> economic aspect
  • Significant reduction of the crack width-limiting reinforcement by more than half -> optimal constructability / economic aspect
  • Greater potential on the resistance side regarding tightness -> durability is crucial
Slab thickness

75 cm Bodenplatte + 80cm Sockel = 155 cm

Execution

combined reinforcement

Concrete

C35/45 FD

Performance class

L2,1/2,1

Fibre type

Dramix® 5D 65/60BG

Owner

BASF SE The Chemical Company

Original solution

SIGMA Pro Consult , Baden Baden

Guirguis, P.; Haus, A.
Flüssigkeitsdichte Bauteile in Kombinationsbewehrung
Bauingenieur Heft 11/2015. / www.bauingenieur.de
Download PDF

back to the list of projects:

Get in touch with our Team!

By phone, email or via social networks:
We are here for you.

Falconix Engineering GmbH
Siemensstraße 24
61267 Neu-Anspach
Germany