City Prag
Living at Theaterviertel BA1 - BA3
Location
Maybachstraße 10A, 10B, 12A-G, 14, Stuttgart-Feuerbach
Construction year2019
Project descriptionCombined reinfocement for the foundation slabs for the residential buildings at Theaterviertel BA1 - BA3.
Optimisation with SFRC
-
The construction process was speeded up due to the use of combined reinforcement
- Reduction of crack width-limiting reinforcement by more than half -> optimal constructability / economic aspect
Slab thickness
70 - 100 cm;
Executioncombined reinforcement
ConcreteC35/45
Performance classL1,8/1,8
Fibre typeDramix® 4D 65/60BG
Owner
Instone Real Estate Development GmbH, Stuttgart
Original solutionFritz Deufel Ingenieurgesellschaft mbH , Deizisau
Floor areaca. 8.300 m²
Cubatureca. 8.000 m³