Nonnenmühlgasse Leipzig

New construction of a multi-storey building

Location

Nonnenmühlgasse, 04107 Leipzig

Construction year

2019

Project description
Combined reinforcement for the foundation slab on a floor area of ​​1,000m² for a six-storey mixed-use building.
Optimisation with SFRC
  • Extensive building geometry and the associated crack width problem
  • The aim was to avoid construction joints in the foundation slab in order to achieve a seamless structure
  • The use of steel fibre reinforced concrete had a positive effect in limiting the crack width due to
    because of the homogeneous distribution and reinforcement of the entire cross section
Slab thickness

50 cm

Execution

combined reinforcement

Concrete

C35/45

Performance class

L1,8/1,5

Fibre type

Dramix® 5D 65/60BG

Owner

St. Elisabeth Krankenhaus Leipzig

Building contractor

Reprobau GmbH

Original solution

D&P Planungsgesellschaft mbH, Leipzig

Floor area

1.000 m²

back to the list of projects:

Get in touch with our Team!

By phone, email or via social networks:
We are here for you.

Falconix Engineering GmbH
Siemensstraße 24
61267 Neu-Anspach
Germany